Works progress
The works of El Lago Club with its leisure facilities, the golf course and the lake itself are well advanced and progressing favourably. Day by day the future lake takes more shape, in these new images you can appreciate the large scale of the project, which becomes more evident as the works progress. El Lago Club is scheduled to be operational in 2026.
The building of El Lago Club is in the last phase of development, the structure has been completed and we are working on the exteriors, equipment and furnishings. The filling of the lake has begun and is currently at 80% of its capacity. As for the water infrastructure, both the technical wetlands and the lake bottom piping network have been completed. The pedestrian walkways, designed to improve the connection with the natural environment, are under construction. The golf course work is progressing at a good pace and all the holes have been completed. The El Lago Club golf course will have 6 holes available for all those who want to enjoy a game at any time of the day while enjoying the breathtaking views.